Nairobi Expressway
Nairobi, Multiple
Infrastructure
Completed
A 27km elevated highway connecting Jomo Kenyatta International Airport to Nairobi's Westlands area, designed to ease traffic congestion in Kenya's capital city.
Project Overview
Timeline
StartedOct 16, 2020
Expected CompletionApr 30, 2022
Actual CompletionMay 14, 2022
Budget
AllocatedKES 65,000,000,000
SpentKES 67,500,000,000
Efficiency96%
Impact
Beneficiaries1,500,000 people
Jobs Created6,000 jobs
Economic ImpactKES 3,500,000,000
SDG Goals
SDG 9
SDG 11
Responsible Parties
Implementing Agency
Kenya National Highways Authority (KeNHA)
Contractors
- China Road and Bridge Corporation (CRBC)
Key Officials
E
Eng. Peter Mundinia
Former Director General, KeNHA
Related Projects
Project Progress
Current status and completion percentage
Overall Completion
100%Timeline
100%
Completed on time
Budget
104%
Of budget utilized
Milestones
2/2
Milestones completed
Project Milestones
Key milestones and their status
Design Approval
Final design approval by KENHA
Completed
Planned: Sep 30, 2020
Actual: Oct 5, 2020
Construction Start
Breaking ground ceremony
Completed
Planned: Oct 15, 2020
Actual: Oct 16, 2020