Nairobi Expressway

Nairobi, Multiple
Infrastructure
Completed

A 27km elevated highway connecting Jomo Kenyatta International Airport to Nairobi's Westlands area, designed to ease traffic congestion in Kenya's capital city.

Project Overview

Timeline

StartedOct 16, 2020
Expected CompletionApr 30, 2022
Actual CompletionMay 14, 2022

Budget

AllocatedKES 65,000,000,000
SpentKES 67,500,000,000
Efficiency96%

Impact

Beneficiaries1,500,000 people
Jobs Created6,000 jobs
Economic ImpactKES 3,500,000,000

SDG Goals

SDG 9
SDG 11
Responsible Parties

Implementing Agency

Kenya National Highways Authority (KeNHA)

Contractors

  • China Road and Bridge Corporation (CRBC)

Key Officials

E

Eng. Peter Mundinia

Former Director General, KeNHA

Project Progress
Current status and completion percentage

Overall Completion

100%

Timeline

100%

Completed on time

Budget

104%

Of budget utilized

Milestones

2/2

Milestones completed

Project Milestones
Key milestones and their status

Design Approval

Final design approval by KENHA

Completed
Planned: Sep 30, 2020
Actual: Oct 5, 2020

Construction Start

Breaking ground ceremony

Completed
Planned: Oct 15, 2020
Actual: Oct 16, 2020