Dongo Kundu Bypass
Mombasa, Likoni
Infrastructure
In Progress
A 17.5km bypass connecting Mombasa Island to the South Coast, reducing travel time and congestion at the Likoni Ferry.
Project Overview
Timeline
StartedMar 10, 2018
Expected CompletionDec 31, 2025
Budget
AllocatedKES 25,000,000,000
SpentKES 15,000,000,000
Efficiency85%
Impact
Beneficiaries700,000 people
Jobs Created3,000 jobs
Economic ImpactKES 1,500,000,000
SDG Goals
SDG 9
SDG 11
Responsible Parties
Implementing Agency
Kenya National Highways Authority (KeNHA)
Contractors
- China Civil Engineering Construction Corporation
Key Officials
E
Eng. Kung'u Ndung'u
Director General, KeNHA
Related Projects
Project Progress
Current status and completion percentage
Overall Completion
65%Timeline
91%
Of timeline elapsed
Budget
60%
Of budget utilized
Milestones
1/1
Milestones completed
Project Milestones
Key milestones and their status
Phase 1 Completion
Completion of Miritini to Kipevu section
Completed
Planned: Jun 30, 2019
Actual: Jul 15, 2019