Dongo Kundu Bypass

Mombasa, Likoni
Infrastructure
In Progress

A 17.5km bypass connecting Mombasa Island to the South Coast, reducing travel time and congestion at the Likoni Ferry.

Project Overview

Timeline

StartedMar 10, 2018
Expected CompletionDec 31, 2025

Budget

AllocatedKES 25,000,000,000
SpentKES 15,000,000,000
Efficiency85%

Impact

Beneficiaries700,000 people
Jobs Created3,000 jobs
Economic ImpactKES 1,500,000,000

SDG Goals

SDG 9
SDG 11
Responsible Parties

Implementing Agency

Kenya National Highways Authority (KeNHA)

Contractors

  • China Civil Engineering Construction Corporation

Key Officials

E

Eng. Kung'u Ndung'u

Director General, KeNHA

Project Progress
Current status and completion percentage

Overall Completion

65%

Timeline

91%

Of timeline elapsed

Budget

60%

Of budget utilized

Milestones

1/1

Milestones completed

Project Milestones
Key milestones and their status

Phase 1 Completion

Completion of Miritini to Kipevu section

Completed
Planned: Jun 30, 2019
Actual: Jul 15, 2019